Saturday, April 20, 2013

New Church building update September 27, 2013


Progress update 9/27/2013

Thanks to all who contributed to this weeks success. We have all the exterior walls finished and most of the classrooms finished. We will be working on Saturday the 28th. 8:30 till 11:30 if anyone wishes to help to finish up the classrooms and clean up some. The gate needs some oiling and maintenance if any one has experience or know how. It is just to hard to open and close. I will try to update picture progress each week. Thanks to the women who have contributed to the drinks and food. God bless all of you who have helped.














Progress Update 9/20/2013

Making progress on the framing. We will be framing the walls with volunteer help Monday through Friday from 8:00 AM till 4:30 P.M. and some Saturday's. You don't have to have a lot of skill to help and every hand is needful. We are using nail guns for most of the nailing but the walls get heavy to lift. Hopefully we will get the Walls finished in a couple of weeks. All help is appreciated and the ladies of the church are providing food and drinks. We are actually enjoying the work and fellowship so please try to stop by even if it is for an hour or so. Most of the help is from retired folk who love the Lord and willing to serve God. Thank all who help.








We will be getting our building permit next week, Loan has been approved and work will get started real soon. Contractor has license and insurance in place to begin work. Hopefully we will be finished in approximately 7 months. Pray that we will be successful and no one gets hurt. Much of our success depends on getting volunteer help from area Christian workers who volunteer to do God's work. Pray! Pray! Pray! And may God have all the Glory and Praise.


New Update: September 7, 2013

      We will start work Tuesday September 10, 2013 building and erecting walls. We will be working on a regular schedule of Monday through Friday beginning at 8:00 AM. We will be working some Saturday's when we can get enough help. We will be using volunteer help to accomplish this building project. If you can volunteer some hours or days please come for we need you. You can post here on this site or let someone from the Church know when you can work and we will make preparations. We are stepping out on faith and trusting that the Lord will take care of all our needs. Please Pray for us that God will watch over and protect and guide us. God bless and spread the word!

3 comments:

Unknown said...

We have our building permit and excavation on the land has been roughed in and ready for compaction test to begin the foundation. Volunteers will be needed soon. Contact Johnny Devine or Wayne Evans if you can add you to the volunteer list.

Unknown said...

Wow! We are coming along with the church. We have poured the foundation, walls and about ready for the concrete floor. Hopefully we will be building and standing up walls in July. We will be needing all the area help we can get to stand up the walls. please call Johnny Devine 865-285-9067 if you can help.

Unknown said...

We will begin building walls for our new church beginning Tuesday Sept 10,2013. We will start work at 8:00am and work Tuesday through Friday of that week. We can use all the help we can get and your prayers. SPREAD THE WORD and may the Lord bless you and the ministry going on at Emory Heights Baptist Church. Let us know and we will add you to the ongoing monthly calendar. 285-9067